單項選擇題

(1) is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the dependencies.This method includes following types of dependencies or precedence relationships: (2) the initiation of the successor activity, depends upon the completion ofthe predecessor activity.(3) the initiation ofthe successor activity, depends upon the initiation ofthe predecessor activity.

空白(1)處填()

A.PDM
B.CPM
C.PERT
D.AOA


你可能感興趣的試題

1.單項選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources

2.單項選擇題

An example of scope verification is ().

A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project

3.單項選擇題

The TCP protocolis a ()layer protocol.

A.physical
B.network
C.transport
D.application