單項(xiàng)選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources


你可能感興趣的試題

1.單項(xiàng)選擇題

An example of scope verification is ().

A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project

2.單項(xiàng)選擇題

The TCP protocolis a ()layer protocol.

A.physical
B.network
C.transport
D.application

3.單項(xiàng)選擇題

The connection between two networks from an intemet is handled by a machine known as a()

A.bridge
B.server
C.router
D.switch

最新試題

An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?

題型:單項(xiàng)選擇題

Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()

題型:單項(xiàng)選擇題

空白(1)處填()

題型:單項(xiàng)選擇題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

題型:單項(xiàng)選擇題

空白(3)處填()

題型:單項(xiàng)選擇題

空白(3)處填()

題型:單項(xiàng)選擇題

Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.

題型:單項(xiàng)選擇題

Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()

題型:單項(xiàng)選擇題

Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

題型:單項(xiàng)選擇題

空白(1)處填()

題型:單項(xiàng)選擇題