Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources
您可能感興趣的試卷
- 2009年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
An example of scope verification is ().
A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project
The TCP protocolis a ()layer protocol.
A.physical
B.network
C.transport
D.application
The connection between two networks from an intemet is handled by a machine known as a()
A.bridge
B.server
C.router
D.switch
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
A.users
B.servers
C.producers
D.suppliers
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
A.share
B.Mitigate
C.Transfer
D.Acceptance
最新試題
An activity has an early start date-of the lOth and a late start date of the 19th. The activity also has a duration of 4 days. There are no nonworkdays. From the information given, ()what can be concluded about the activity?
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
空白(1)處填()
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
空白(3)處填()
空白(3)處填()
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
空白(1)處填()