單項(xiàng)選擇題

There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.

A.share
B.Mitigate
C.Transfer
D.Acceptance


你可能感興趣的試題

4.單項(xiàng)選擇題

Contract closeout is a process that involves()

A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout

5.單項(xiàng)選擇題

In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix