PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
您可能感興趣的試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
The()defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
最新試題
空白(2)處填()
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
空白(2)處填()
The TCP protocolis a ()layer protocol.
空白(3)處填()
空白(1)處填()
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
空白(1)處填()
空白(3)處填()
You are working on the cost budget for one project. Which of the following is true()