The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
您可能感興趣的試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2009年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2010年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
- 2011年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師下半年上午試卷
- 2012年計算機技術與軟件專業(yè)技術資格高級信息系統(tǒng)項目管理師上半年上午試卷
你可能感興趣的試題
A.project scope statement
B.project requirement
C.project charter
D.product specification
The()provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B.contract
C.project human resource plan
D.projectcharter
The()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
The()defines the phases that connect the beginning of a project to its end.
A.schedule
B.project life cycle
C.temporary
D.milestone
()means that every project has a definite beginning and a definite end.
A.Projectphase
B.Unique
C.Temporary
D.Closure
最新試題
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
空白(1)處填()
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
空白(1)處填()
Contract closeout is a process that involves()
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
空白(1)處填()