()is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
A.Method
B.Polymorphism
C.Inheritance
D.Encapsulation
您可能感興趣的試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2009年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2010年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
- 2011年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師下半年上午試卷
- 2012年計(jì)算機(jī)技術(shù)與軟件專業(yè)技術(shù)資格高級(jí)信息系統(tǒng)項(xiàng)目管理師上半年上午試卷
你可能感興趣的試題
The strategies for handling risk comprise of two main types: negative risks, and positive risks. The goal ofthe plan is to minimize threats and maximize opportunities. When dealing with negative risks, there are three main response strategies(),rransfer ,Mitigate.
A.Challenge
B.Exploit
C.Avoid
D.Enhance
The ()process ascertains which risks have the potential of affecting the project and documenting the risks' characteristics.
A.Riskldentification
B.Quantitative Risk Analysis
C.Qualitative Risk Analysis
D.Risk Monitoring and Control
Developing the project schedule is often an iterative process. It determines the planned start and finish dates for project activities and milestones. Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to()progress.
A.analyze
B.track
C.level
D.extend
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.
A.milestone
B.baseline
C.quality
D.work
Project work packages are typically decomposed into smaller components called activities to provide a basis for()scheduling, executing, and monitoring and controllingthe proj ect work.
A.reviewing
B.estimating
C.auditing
D.expecting
最新試題
Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.
空白(4)處填()
You are working on the cost budget for one project. Which of the following is true()
空白(2)處填()
An example of scope verification is ().
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project's communication. According to Metcalfe's Law, a project with 10 stakeholders has()potential communication channels.
空白(1)處填()
空白(2)處填()
Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().