The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned, designed and built in, not()
Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.