單項(xiàng)選擇題While using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?()

A.NPIV and vSCSI both require multipathing in VIO Server only. 
B.NPIV requires multipathing software on client LPARs, vSCSI requires multipathing software on VIO Server. 
C.NPIV requires multipathing software on VIO Server, vSCSI requires multipathing software on client LPARs. 
D.NPIV requires multipathing and MPIO software on VIO Server LPARs, vSCSI requires multipathing software on VIO Server and MPIO on client LPARs.


您可能感興趣的試卷

你可能感興趣的試題

1.單項(xiàng)選擇題

A customer is installing an HMC-managed Power 720 with two partitions, one for Production the other for Testing. They plan to use the Testing partition only occasionally and want to minimize hardware.
Which of the following meets these requirements?()

A.Create a system profile for each partition. Assign all needed resources as 'required'.
B.Define all system resources as 'desired' on the Testing partition. Activate only as needed.
C.Create two shared processor pools. Assign the minimal I/O resources required for each partition to the shared pools.
D.Create both partitions with minimal 'required' resources, and optional resources as 'desired'. Activate each partition as necessary.

2.單項(xiàng)選擇題How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()

A.Use Capacity on Demand to add the resources.
B.Use DLPAR to add the resources and select the 'permanent' option.
C.Use DLPAR to add the resources, and change the partition profile.
D.Use an Operating System command to permanently request the resources.

3.單項(xiàng)選擇題Which of the following includes Active Memory Sharing (AMS)?()

A.PowerHA Enterprise Edition
B.PowerVM Enterprise Edition
C.VMControl Enterprise Edition
D.Systems Director Enterprise Edition

5.單項(xiàng)選擇題

A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window. 
Which solution addresses this problem without requiring additional hardware?()

A.Adding VMControl will automate processor resource allocation during peak workloads 
B.Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors.
C.Add processing resources during the times they are required using Utility Capacity on Demand.
D.Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads. 

最新試題

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which  also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed  systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.How can they manage the new machines for the least cost?()

題型:?jiǎn)雾?xiàng)選擇題

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

題型:?jiǎn)雾?xiàng)選擇題

A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()

題型:?jiǎn)雾?xiàng)選擇題

A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?()

題型:?jiǎn)雾?xiàng)選擇題

A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.Which action will reduce the potential vendor software costs?()

題型:?jiǎn)雾?xiàng)選擇題

A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()

題型:?jiǎn)雾?xiàng)選擇題

A customer requires two 12X loops on their new POWER7 system. What is the smallest system that will support two loops?()

題型:?jiǎn)雾?xiàng)選擇題

An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.Which Blade is designed for Windows workloads?()

題型:?jiǎn)雾?xiàng)選擇題

A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3).Which of these statements is true and would minimize the cost?()

題型:?jiǎn)雾?xiàng)選擇題

Which of the following has an integrated database?()

題型:?jiǎn)雾?xiàng)選擇題