單項選擇題

A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached One 4-port 1Gbps IVE adapter PowerVM Standard Edition. They need to add a GX++ adapter and cable it to an I/O drawer.
Which of the following must also be ordered?()

A.A second IVE adapter
B.A second processor card
C.PowerVM Enterprise Edition
D.An additional cable-management arm


您可能感興趣的試卷

你可能感興趣的試題

2.單項選擇題The Power 720 is offered with how many cores?()

A.1, 2, or 4
B.2, 4, or 6
C.2, 4, or 8
D.4, 6, or 8

3.單項選擇題Which of the following solutions provides maximum core density per rack?()

A.Power 730
B.PS700 Blades
C.PS702 Blades
D.PS703 Blades

5.單項選擇題Which system provides the highest performance per core, and the least cost for applications licensed per core?()

A.A Power 795 with MaxCore mode
B.A Power 780 with MaxCore mode
C.A Power 755 with TurboCore mode
D.A Power 780 with TurboCore mode

最新試題

Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()

題型:單項選擇題

Which system provides the highest performance per core, and the least cost for applications licensed per core?()

題型:單項選擇題

Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()

題型:單項選擇題

A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()

題型:單項選擇題

A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()

題型:單項選擇題

A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()

題型:單項選擇題

A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()

題型:單項選擇題

While using virtualization to share SAN adapters on a server, how does Node Port ID Virtualization (NPIV) differ from Virtual SCSI (vSCSI) related to the use of multipathing software?()

題型:單項選擇題

A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()

題型:單項選擇題

Which operating system can directly host managed storage for IBM i, AIX, Linux, VMware and Windows on a Power Systems server?()